During the visit, Mr. Henari, along with a number of senior executives from MAPNA Development & Investment Company, also attended the site and, while accompanying the visiting delegation, presented a report on the latest project status, progress of activities, and completed construction works
The operational status of the GIS substation and the liquid-fuel piping works at the power plant were subsequently reviewed, and the latest progress of these activities was presented.
The Rey Medium-Scale Power Plant is being constructed with three 42 MW gas-fired units. To date, two units have been completed and successfully synchronized with the national power grid. Construction of the third unit is scheduled to commence in the near future
The project is located in Rey County, Tehran Province, and is being implemented for the Thermal Power Plants Holding Company, with Qods Niroo Engineering Company providing engineering consultancy services.