The third unit in the steam section of Ferdowsi Combined-Cycle Power Plant was successfully synchronized to the Iranian nationwide power grid on Wednesday, July 22, 2026 at 22:45. The remarkable

On Wednesday, July 15, 2026, a visit was paid by Mr. Amiri (Engineering), CEO of MAPNA’s Iranian Power Plant Management Group and Mr. Mohammadkazemi (Engineering), CEO of MAPNA’s Tous Power

At 3:03 AM on Tuesday, June 30, 2026, Fazel Abad Substation as a part of the Mazandaran-Golestan Power Transmission Project was connected to the power grid.The Mazandaran-Golestan Power Transmission Project

On Sunday, June 29, 2026, Rashed Block-Type Power Plant in the city of Torbat-e-Heydarieh was paid a visit by Mr. Espanani (Engineer), Project Deputy Director of Thermal Power Generation Holding